High Efficient,Reliable,Convenient---

MOBILE CRUSHER

Vertical Roller mill operation step by step with images

All access doors should be checked before starting the mill, shut down are tight, check crusher jaw gap compliance with feed grain size to adjust analysis machine speed should be up to the approximate finished size requirements. Last boot in the following order:

1, starting bucket elevator;
2, starting jaw crusher;
3, Material pending silo there, start the analysis machine;
4, start the blower (empty load to start, and then to be the normal operation of loading);
5, start the host, at the moment the start the host starts electromagnetic vibrating feeder. The Mill is the beginning. Operating order summary said: “start” upgrade, crusher, analysis machine, fan, host feeder.

Stopping off for each machine should be stopped in the following order:

1, first turn off the feeder stop feeding;
2, After about a minute, stop feeding;3, stop blowing the net residual powder sub blower;
4, the final closure of the Analytical Engine.
The shutdown sequence is: feeder, host, blowers, analysis;

Note: the Hoist transport materials to a certain amount silo, first stop the crusher and then stop upgrading this should be storage quantity varies.

Vertical Roller mill operation step by step with images

Vertical Roller mill operation step by step with images

5, vertical roller mill in normal working hours may not be disposed refueling, to ensure production safety, Mill occur in any part of the unusual noise, or sudden load increase should immediately check, troubleshooting, and to avoid a major accident. Continue to re-boot more than expected in the mill must be removed, otherwise the power current is too large, the impact of start.

Now, you can OR to get price and product manual!

Other Crushing and Grinding Equipment

In order to recommend you the most suitable plant, you are kindly requested to tell us the below information:

1 what kind of stone do you want to crush?
2 what is the material size before crushing?
3 what is the final product size do you want?
4 what is the capacity you want tons per hour?
5 what will you do with the final products?